Inspection Report
Silom Tower B
Silom District, Bangkok · Mixed-use high-rise
Mission ID
M-20260628
Survey Date
28 June 2026
Duration
38 min
Max Altitude
25.6 m
Progress
78%
Compliance
85%
within 1 cm tolerance
BIM Deviation Stats
Maximum deviation4.2 cm
Average deviation0.9 cm
Compliance (≤1 cm)85%
5 defects detected. Critical crack on Floor 3 NW requires immediate attention. Rebar exposure on Floor 5 unchanged. 3 medium-severity items added.
2Critical
2Medium
1Low
AiRial · DINOv3 inference
Detected Defects
| Defect ID | Type | Location | Deviation | Confidence | Severity |
|---|---|---|---|---|---|
| D-0628-01 | crack | Floor 3 · north | 3.8 cm | 94% | critical |
| D-0628-02 | rebar exposure | Floor 5 · south | 4.2 cm | 91% | critical |
| D-0628-03 | spalling | Floor 2 · east | 2.8 cm | 87% | medium |
| D-0628-04 | misalignment | Floor 6 · north | 2.1 cm | 82% | medium |
| D-0628-05 | water staining | Floor 1 · west | 0.8 cm | 76% | low |