Inspection Report

Silom Tower B

Silom District, Bangkok · Mixed-use high-rise

Mission ID

M-20260628

Survey Date

28 June 2026

Duration

38 min

Max Altitude

25.6 m

Progress

78%

Compliance

85%

within 1 cm tolerance

BIM Deviation Stats

Maximum deviation4.2 cm
Average deviation0.9 cm
Compliance (≤1 cm)85%

5 defects detected. Critical crack on Floor 3 NW requires immediate attention. Rebar exposure on Floor 5 unchanged. 3 medium-severity items added.

2Critical
2Medium
1Low
AiRial · DINOv3 inference

Detected Defects

Defect IDTypeLocationDeviationConfidenceSeverity
D-0628-01crackFloor 3 · north3.8 cm94%critical
D-0628-02rebar exposureFloor 5 · south4.2 cm91%critical
D-0628-03spallingFloor 2 · east2.8 cm87%medium
D-0628-04misalignmentFloor 6 · north2.1 cm82%medium
D-0628-05water stainingFloor 1 · west0.8 cm76%low